Loss

At a glance…

The loss node loses flow based on a provided flow-loss relationship.

[node.high_flow_loss]
type = loss
loc = 20, 30
table = 0, 0,
        1000, 0,
        2000, 500,
        1e8, 1e7
ds_1 = node_below_loss

Node properties

Property Description
[node.?] (compulsory) Start of node declaration. This says we are creating a node, and also defines the name of the node. Node naming conventions are discussed at . Example: [node.high_flow_loss]
type (compulsory) The node type, which is “loss” in this case. type = loss
loc (compulsory) The location of the node in cartesian coordinates. Example: loc = 20, 30
table (optional) Loss table defines the relationship between the upsteam flow and the loss. Refer to this page to read more about in Kalix. Example: table = 0, 0, 1000, 0, 2000, 500, 1e8, 1e7
rate (optional) Loss rate override: a data reference, constant, or dynamic expression. When set, the loss is taken from this value each timestep instead of the loss table (the table, if also present, is ignored for computing loss but still shapes ordering — see below). The value is clamped between 0 and the upstream flow. Example: rate = data.losses.reach_3
ds_1 (optional) Name of the downstream node. This property defines a downstream link. Inflow nodes may only have 1 downstream link. Example: ds_1 = my_other_node

Results associated with this node

Result Description
dsflow Total downstream flow (=ds_1) [ML]
usflow Upstream flow [ML]
ds_1 Downstream flow on link ds_1 [ML]
ds_1_order Orders on the link ds_1 [ML]
loss Amount of water lost at this node [ML]
rate The evaluated rate expression (before clamping) [ML]. All missing values when no rate property is set.

How the node works

The attempted loss is determined by interpolating the provided loss table against the upstream flow — or, when the rate property is set, by evaluating that expression instead. The loss actually taken is the attempted loss clamped between 0 and the upstream flow, and the remainder continues to ds_1.

loss=f(usflow) (table) or loss=rate (override)

ds1=usflow−loss

Note on ordering: upstream orders are translated through the loss table in both cases. A rate expression overrides how much water is actually lost, but ordering has no way to foresee an arbitrary expression's value, so it keeps using the table — supply a representative table alongside rate if downstream orders should account for expected losses (with no table, ordering assumes zero loss).

References